PJM is proposing a new Expedited Interconnection Track (EIT) to fast-track large generators serving massive new loads—bypassing its traditional queue process. (Renewable Energy World)
Projects must exceed 500 MW, be state-sponsored, and reach commercial operation within three years—a high bar that likely favors battery storage over gas, wind, or nuclear.
Developers would shoulder all network upgrade costs and post a $10K/MW readiness deposit, capped at 10 projects per year.
PJM says the plan addresses capacity shortfalls tied to data center growth, but critics warn the requirements may be too ambitious to attract real projects.