News
FERC Proposes To Update NERC Reliability Standards For Renewable Resources And Energy Storage

On
- Broaden the scope of IBRs that would be required to register with NERC and comply with NERC Reliability Standards.
- Modify existing Reliability Standards to provide registered entities with planning and operational authority the information necessary to more accurately model and plan for the impact of IBRs.
- Establish more uniform guidance regarding the types of changes to IBRs and other facilities that would require evaluation and approval through a transmission provider's interconnection process, including changes to certain control settings.
The orders are a response to a series of NERC reports and white papers that determined that IBRs had exacerbated reliability events by tripping or ceasing production in response to line losses and other system contingencies. For instance, in issuing these orders, the Commission acknowledged that NERC had identified 12 events during which an average of 1,000 megawatts (MW) of IBRs entered into momentary cessation or tripped in response to transmission line faults, thereby exacerbating the potential reliability impact of these events.
Below we provide an overview of
I. Registration of IBRs
In recognition that certain IBRs are currently not required to register with NERC or comply with NERC Reliability Standards, the Commission issued an order directing NERC to take steps to modify its registration criteria to account for the growing impact of IBRs.1
The Commission noted that NERC's existing registration criteria currently exclude many IBRs, as these resources often are smaller than conventional generation resources and are connected at voltages of less than 100 kV. And while NERC has the discretion to require entities to register with NERC if they are determined to have a material impact on system reliability—even when they do not meet applicable criteria—NERC historically has not applied this authority to require the registration of IBRs that, in the aggregate, can have a material impact on the reliable operation of the grid. As a result, the Commission's order concludes that the current registration criteria do not address the "potential impacts to the reliability of the Bulk-Power System of the increasing numbers of small non-BES Bulk-Power System-connected IBRs."2
To close this gap, the order directs NERC to develop and file a work plan for
While directing NERC to take steps to register IBRs, the Commission's order also acknowledges that NERC should have flexibility in determining what Reliability Standards should apply to IBRs given the characteristics of these resources. Specifically, the Commission explained that "NERC may determine that the full set of Reliability Standard Requirements otherwise applicable to generator owners and operators need not apply to currently unregistered IBR generator owners and operators when they are registered."4 Thus, NERC may determine that IBRs that are registered by NERC under its expanded criteria need to comply with the full range of requirements that typically apply to generation owners and operators.
II. NOPR on Reliability Standards for IBRs
The Commission concurrently issued a Notice of Proposed Rulemaking (NOPR) proposing to direct NERC to submit new or modified Reliability Standards that the Commission believes are necessary to address reliability gaps pertaining to IBRs, including IBRs interconnected to distribution networks that can have a material impact on reliability in the aggregate.5 More specifically, the NOPR proposes to require NERC to revise the Reliability Standards to address gaps in four areas: data sharing; data and model validation; planning and operational studies; and performance requirements. Comments on the NOPR will be due 60 days after publication in the
A. Data Sharing
The Commission explains that existing Reliability Standards fail to ensure that registered entities with planning and operating authority (e.g., transmission planners and balancing authorities) receive accurate and complete information on the location and characteristics of IBRs necessary to properly anticipate and respond to the behaviors of IBRs on their systems. Thus, the Commission proposes to direct NERC to develop new or modified standards that:
<ul- Require identified registered entities to provide data on all IBRs (whether registered with NERC or not), establish minimum categories of data that must be provided and establish a schedule for the sharing of IBR data needed for modeling, operations and disturbance analysis.
- Require owners or operators of registered IBRs to provide registered IBR-specific modeling data and parameters (e.g., control settings) to registered entities with planning and operating authority.
- Require transmission owners to share modeling data and parameters for unregistered IBRs in their transmission owner areas.
- Require distribution providers to share modeling data and parameters for distribution-interconnected IBRs in their distribution provider areas.
B. Data and Model Validation
The Commission also concludes that existing Reliability Standards fail to ensure that planning and operating authorities have models that accurately represent the performance of all generation resources, including registered and unregistered IBRs, and that these models are validated and updated based on actual operational behavior.
C. Planning and Operational Studies
The Commission also proposes to require NERC to modify its Reliability Standards to ensure that planning coordinators and transmission planners account for the individual and aggregate behavior of all IBRs, whether registered or not, in their planning areas. The Commission states that these assessments should focus in particular on "ride through" performance of such resources during grid disturbances, as inability to ride through is the primary source of currently-unaddressed IBR instability. On the operational side, NERC must ensure that reliability coordinators, transmission operators, and balancing authorities also include the same individual and, more importantly, aggregate performance of these same IBR resources.
D. Performance Requirements
The Commission also proposes to require NERC to subject IBRs to new performance requirements to ensure that these resources ride through system frequency and voltage disturbances, including:
<ul- Requiring IBRs to use appropriate settings that will assure frequency ride through during system disturbances and limit resource tripping.
- Preventing IBRs from artificially restricting their ramp rates and requiring them to communicate ramp rates to certain registered planning and operational authorities.
- Maintain voltage phase angle synchronization with the grid during a system disturbance.
III. Order Approving NERC Reliability Changes to Clarify Changes to IBRs Requiring Transmission Planner and Planning Coordinator Review
In order to resolve this uncertainty, the revised FAC Reliability Standards approved by
Under the implementation plan approved by
Footnotes
1 Registration of Inverter-based Res., 181
2 Id. at P 33.
3 Id. at PP 1, 5.
4 Id. at P 34.
5 Reliability Standards to Address Inverter-Based Res., 181
6 N. Am. Elec.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.
20006-1037
Tel: 202.887.4000
E-mail: Jlarivee@akingump.com; pazimi@akingump.com
URL: www.akingump.com
Discussions
No discussions yet. Start a discussion below.
Get Published - Build a Following
The Energy Central Power Industry Network® is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.
If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.
Sign in to Participate