
Utility Management Group
Senior decision-makers come together to connect around strategies and business trends affecting utilities.
Post
Plan to Zero (#18) Get out of the Way III
- Plan to Zero
- Plan to Zero - Stop! Don't Do That!
- Plan to Zero - Nega-Watts!
- Plan to Zero - Baseload
- Plan to Zero - Made in the USA
- Plan to Zero - Do No Harm
- Plan to Zero - The electric super speed way
- Plan to Zero - Load Growth
- Plan to Zero - Get out of the Way
- Plan to Zero - Power to the People
- Plan to Zero - This means you!
- Plan to Zero - Measure it Right
- Plan to Zero - Figure it Out
- Plan to Zero - Now Hiring
- Plan to Zero - Another Link in the Value Chain
- You got to know when to hold them…
Red tape…delays…hearings…lawsuits…studies…BANANA’s
Our world is full or regulatory and legal delays.
Interconnect permission 3-7 years.
FERC Hydropower relicensing 8-years, new permit 15 years.
NRC licensing 7 to 12 years.
State hearings on new transmission lines 2 to 13 years.
FERC approvals on new transmission line 4 to 14 years.
Many plans hinge on new transmission, new nuclear, new solar, wind and storage for 2035.
Sorry, if your application is not already in process, likely whatever you need likely will not make it when you add 2 to 5 years for equipment to be delivered.
For projects that are 2-3 Megawatts (MW) in size you can likely skip much of the permitting and permission. At that small size, you can deal directly with the distribution utility.
But to replace a 1-gigawatt (GW) coal plant you need to build over 2,000 3MW solar farms,] and roughly 6,000 3 MW by 4-hour storage projects to fully replace that coal plant 24/365.
Most distribution utilities can handle 2-10 projects a month of this size, and one per circuit of each solar and storage. You are looking at 800 months to interconnect all 8,000 sites (solar and separate storage), and you need roughly 3,000 circuits – about the number that a 3 million customer utility would have typically.
That same utility in a Polar Vortex or heat dome would need 8-17 GW of generation to supply 3 million customers.
What do we do?
Start with changing the law.
Regulatory agencies have from the day of application to a decision 18 months, if they don’t finish, it is automatically approved. Narrow the grounds for disapproval, and for lawsuits. All Federal agencies are on the exact some timeline. Environmental and other studies must be complete before applying. Missing data stops the application, but the agency has 15 business days to determine information is missing.
No notice of missing data, then the decision must be made in 18 months with the data they have in hand.
Similar laws and regulations for ISO/RTO. Model laws from DOE need to be used by the regulatory assistance projects to get them passed at the state level too, so state level reviews are done in the same 18-month time. Rejection criteria need to be technical in nature and specific.
Equipment certification needs to be on a similar timeline, apply and the agency (e.g., the NRC) has 18 months to approve or deny. In most cases the bias must be to approve, not deny.
A Federal ombudsman needs to bird dog the process, across all agencies, state, federal and local. They need to have the authority to remove barriers.
If needed ombudsman need to ability to wield eminent domain.
Get Published - Build a Following
The Energy Central Power Industry Network® is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.
If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.
Sign in to Participate