Steam Turbine Rotor Steeple indications and Diaphragm Repairs

Posted to MD&A in the Generation Professionals Group
image credit: MD&A
Jay Eldridge's picture
Vice President Sales & Marketing MD&A

Bachelor of Science (BS) in Mechanical Engineering with a Mathematics Minor from Union College.  28 years’ experience working in the power generation industry.  Almost 17 of those years were...

  • Member since 2013
  • 40 items added with 56,059 views
  • Mar 11, 2022
  • 838 views

Mechanical Dynamics & Analysis (MD&A) experts recently completed steampath inspection and repair services for a customer during a major overhaul. The Alstom® steam turbine consisted of an HP/IP turbine (stages 1-15) and a single flow LP turbine (stages 16-21).

A detailed incoming inspection was performed for the HP/IP and LP rotors and found relevant indications in the LP rotor steeples at L-1 (stage 20) through magnetic particle inspection, in addition to minor damage identified on the HP/IP rotor. 

Finding indications in the last-stage LP rotor steeples (also known as fir-tree grooves) is a common issue.  Basically, the steeple indications are caused by corrosion fatigue (when a material degrades due to the combination of corrosion and cyclic stresses).

Repair of the LP rotor included removal of the L-1 steeple indications by hand tooling, followed by blending and polishing. There were 3 steeple indications which were noticeably deeper than the rest. The approximate depth of these deeper indications was 3 mm (0.12”) located on the convex side of the steeple.

 

A finite element analysis was performed to verify the structural integrity of the steeples after grinding. Based on the analysis, the L-1 steeple repair was found to be acceptable. After all rotor repairs were complete, the rotors were balanced, and the journals were strapped lapped prior to leaving the workshop.

Incoming inspections were also completed on the HP/IP and LP diaphragms.  The HP/IP diaphragms arrived at the workshop with the lower half appendages removed for reverse engineering. Minor damages were noted on the LP diaphragms including horizontal joint erosion and foreign object damage to the partition trailing edges on all stages, as well as damage to the steam seal face on stages 17-21.

Repair work to the HP/IP diaphragms included installing new appendage rings with honeycomb seals, which were supplied by MD&A Parts.  To ensure proper fitting, the appendage and bore packing fit diameters were machined round prior to installation of the new appendages. Additionally, the dowel pins were removed, and the horizontal joint was skim cut.  Dowel pin holes were then enlarged, and oversized dowel pins were installed.

 

New bore packing (with honeycomb seals) for stages 2-9 and 11-15 were also supplied by MD&A Parts.  The bore packing was test fitted after appendage installation.

Minor repairs were performed on the LP diaphragms including horizontal joint weld repairs and removal of broken studs. After all diaphragm repairs were complete, new horizontal joint hardware was supplied by MD&A Parts and test-fitted before the diaphragms left the workshop.

Through MD&A’s state-of-the-art repair facility and quick access to replacement parts, an extensive inspection and necessary repairs were completed by our experts in a timely manner that allowed the unit to be quickly returned to site.  We are your full-service, OEM-alternative! Call MD&A today at +1 (314) 880-3000!

Also be sure to sign up for our MD&A Insight e-newsletter delivered quarterly. Get our turbine-generator expert’s case studies and tips! Fill in sign up form and SUBSCRIBE!

Connect with MD&A

Fill out this form to receive more information from MD&A.

MD&A
Mechanical Dynamics & Analysis (MD&A) provides power generators around the globe with a full-service, OEM-alternative for services, parts, and repairs for Gas Turbines, Steam Turbines and Generators.
RECENT POSTS FROM THIS COMPANY
Jay Eldridge's picture
Thank Jay for the Post!
Energy Central contributors share their experience and insights for the benefit of other Members (like you). Please show them your appreciation by leaving a comment, 'liking' this post, or following this Member.
More posts from this member

Discussions

Spell checking: Press the CTRL or COMMAND key then click on the underlined misspelled word.

No discussions yet. Start a discussion below.

Get Published - Build a Following

The Energy Central Power Industry Network is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.

If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.

                 Learn more about posting on Energy Central »