Pleasant Prairie reaches water pipeline agreement with We Energies

  • Aug 12, 2022
  • 79 views
Source: 
WITI-TV

PLEASANT PRAIRIE, Wis. - Pleasant Prairie and We Energies announced an "in-place abandonment" agreement for water pipelines after a coal-fired power plant was demolished Saturday, Aug. 6.

The power plant was in operation from 1976 to 2018, and We Energies began decommissioning the site in 2020. Throughout the abandonment process, the village said, the two parties worked on a plan to address the pipelines, which connected the former plant to Lake Michigan.

On Aug. 8, the village board approved the agreement to abandon three water pipelines in place, including:

* An original 30-inch intake line that was shut down in 1988

* A replacement 30-inch intake line that was in use until 2018

* An 18-inch line that was used intermittently to discharge rainwater after the plant was shut down

Instead of filling the lines with slurry, We Energies provided an alternative pipeline abandonment plan to Pleasant Prairie. The agreement allows We Energies to abandon the waterlines without fill or removal.

"The village plans to remove the abandoned water pipelines as needed," said Jean Werbie-Harris, Pleasant Prairie community development director. "The water lines are well constructed and not at risk of failure, which gives the village sufficient time to approach the project cost-effectively."

SIGN UP TODAY: Get daily headlines, breaking news emails from FOX6 News

We Energies will make a one-time payment to the village of Pleasant Prairie, totaling $412,500. The village will assume ownership and responsibility for the portions of retired pipelines within the public right of way.

Additionally, the agreement states We Energies will retain responsibility and obligations for the sections of retired waterlines within private property, per the village.

Discussions
Spell checking: Press the CTRL or COMMAND key then click on the underlined misspelled word.

No discussions yet. Start a discussion below.

Get Published - Build a Following

The Energy Central Power Industry Network is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.

If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.

                 Learn more about posting on Energy Central »