NUCLEAR POWER PLANTS - CEZ WILL SHUT DOWN THE TEMELIN UNIT 2 FOR CHECKING AND REPLACING FUEL ASSEMBLIES TODAY

Checks of safety systems, of the turbine, 69 investment actions or the replacement of a part of fuel assemblies.
These are just examples of the most important works to be carried out during the planned Unit 2 outage of the Temelin Nuclear Power Plant. The technicians will disconnect the Unit from the transmission system tonight. Overall, CEZ company plans to do almost fifteen thousand activities, which it preliminarily designed for two months.
The technicians plan the actual trip of the Unit 2 generator from the transmission system for today evening at approximately one-third of the reactor rated output. According to the power plant management, this will be a standard outage associated with essential checks and investment activities.
'We will replace 48 of the total 163 fuel assemblies; for example, we will check safety divisions, the main circulation pump or the containment building tensioning system around the reactor. Also, the turbine will undergo a detailed inspection,'
said
The technicians are also facing 69 investment actions aimed at modernizing and further strengthening the power plant's safety. Such an example will be the modernization of the generator exciter control system or the modernization of an important safety system that provides power supply to the backup batteries.
For CEZ, this is the fifth of this year's six nuclear power plant outages. Last week, energy workers connected the Dukovany Unit 1 after a two-month outage. CEZ company coordinates the outages of Temelin and Dukovany so that their confluence is minimal.
'This is important in terms of the suppliers' transmission system and personnel capacity, who mostly carry out the same activities at both power plants. In this case, too, the beginning of the outage of the Temelin Unit 2 and the end of the outage of the Dukovany Unit are linked,'
said
Including the external suppliers, around one thousand people are involved in the outage works. It is the final planned outage at Temelin this year. Unit 1 has been shut down for inspection and replacement of fuel assemblies for less than two months, from 7 April to 8 June.
Since the beginning of the year, the Temelin power plant has produced 10.3 terawatt hours of electricity. Together with Dukovany, these sources make the most considerable amount of clean electricity and thus contribute significantly to
Contact:
Tel: + 420 211 042 529
Discussions
No discussions yet. Start a discussion below.
Get Published - Build a Following
The Energy Central Power Industry Network® is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.
If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.
Sign in to Participate