News
B.C. Hydro's Integrated Resource Plan, EPA Renewals Other Key Developments In B.C.'s Power Sector In 2022

This article forms part of our Power Perspectives 2023 publication. Download the full publication here.
Several developments relating to BC Hydro continue to lay the groundwork for BC's energy future, including the completion of Phase 2 of the province's comprehensive review of the provincial utility and the submission by BC Hydro of its first integrated resource plan (IRP) in almost a decade.
While BC Hydro's new IRP works its way through regulatory review, the utility continued to advance construction of its Site C hydroelectric facility (Site C) while reaching an important settlement with litigants challenging the project.
BC Hydro expects to have sufficient energy and capacity until the early 2030s, and accordingly there continues to be no new material procurement opportunities for independent power producers (IPPs) in BC. However, BC Hydro does intend to renew existing electricity purchase agreements (EPAs") for clean or renewable projects set to expire before
BC Hydro Integrated Resource Plan Update
As we reported in last year's publication, in
- continuing the use and implementation of customer-based solutions through demand-side measures (such as energy efficiency and conservation programs);
- ensuring preparedness for future electricity needs—higher electricity demand due to electrification or lower demand resulting from economic downturns; and
- incorporating the United Nations Declaration on the Rights of Indigenous Peoples and the Truth and Reconciliation Calls to Action in its plan.
The IRP currently remains under review by the
As detailed below, 2022 saw notable advances in the
Site C Update
BC
Key construction milestones in 2022 included the placement of the final penstock segment, completing the project's six penstock units; ongoing placement of materials at the earthfill dam; approach channel excavations; right bank foundation enhancements; and the realignment of
According to BC Hydro, key challenges faced by the project as it proceeds toward completion include attracting and retaining sufficient skilled craft labour; inflationary pressures and interest rate increases; potential additional mitigation measures for acid-generating rock; the potential re-emergency of COVID-19 cases on site; commercial negotiations with contractors; possible design changes due to unknown field conditions; and obtaining all of the remaining permits required for project completion.
Perhaps the most significant development in 2022 occurred on
- an impact benefit agreement between BC Hydro and West Moberly;
- two agreements between BC Hydro and West Moberly that provide West Moberly certain contracting opportunities;
- a tripartite land agreement between the BC government, BC Hydro and West Moberly;
- an agreement providing for the release of West Moberly's claims against the Site C project; and
- a separate settlement agreement between the Canadian federal government and West Moberly.
In the remainder of its civil claim, West Moberly has asserted that the existing hydroelectric dams on the
As proposed in its IRP, BC Hydro is developing an electricity purchase agreement renewal program for IPPs that have EPAs for clean or renewable projects set to expire prior to
Under the
- A term of either five or 20 years.
- In the case of EPAs with a five-year term, an energy price for delivered energy which is based on the applicable Mid-C price at the time of delivery, to a maximum of
$80 /MWh (USD), adjusted depending on whether net aggregate power flows from both theBritish Columbia -United States andBritish Columbia -Alberta interties are in a net export or a net import position. - In the case of EPAs with a 20-year term, an energy price for delivered energy of
$58 /MWh, adjusted annually for CPI, subject to a deduction for line losses based on the project's location within BC, and adjusted by a time-of-delivery factor ranging from 50% to 150% depending on the month of delivery and whether the delivery is during on-peak or off-peak hours. - A seller may choose not to generate during the freshet season if
EPA prices are uneconomic. - All environmental attributes for delivered energy are transferred to BC Hydro.
- No liquidated damages are payable by the seller for non-delivery.
Based on the other terms set out in the final draft term sheet, it appears that the form of the renewal
- BC Hydro may curtail deliveries for safety or system security or reliability issues at any time (i.e., an emergency condition), and the seller must comply with BC Hydro's directions, with no payments being made to the seller during the emergency condition.
- BC Hydro has the right to curtail deliveries for any reason other than an emergency condition, provided BC Hydro will pay for deemed energy that could have been delivered by the seller during a curtailment due to a BC Hydro system constraint after the first 72 continuous hours of the system constraint. This is similar to the provisions in the last SOP
EPA , however in that case BC Hydro would pay for deemed energy after the first 24 hours of curtailment in the aggregate in any month. - If the seller is in material default and BC Hydro exercises its termination right, the seller must pay a termination payment equal to the greater of: <ul
- an amount equal to the positive amount, if any, by which BC Hydro's economic losses and costs exceed the aggregate of BC Hydro's gains from the termination; and
$4,000 x plant capacity x years remaining before theEPA expires.- No payment is owing by BC Hydro if the seller terminates for any reason.
The above provisions will likely be concerning to sellers considering entering into a renewal
In
To view the original article click here
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.
Canadian Energy Perspectives
McCarthy Tétrault LLP
Suite 5300,
ON M5K 1E6
Tel: 416362 1812
Fax: 416868 0673
E-mail: info@mccarthy.ca
URL: www.mccarthy.ca
Discussions
No discussions yet. Start a discussion below.
Get Published - Build a Following
The Energy Central Power Industry Network® is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.
If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.
Sign in to Participate