Transmission Facilities - EV

Paul Dumais's picture
CEO Dumais Consulting

Owner and CEO of Dumais Consulting (www.DumaisConsulting.com) which provides expert ratemaking services to energy companies. Dr. Dumais is a ratemaking and regulatory expert who specializes on...

  • Member since 2018
  • 149 items added with 114,728 views
  • Nov 25, 2020
  • 371 views

On November 16, 2020, in ER21-424, Michigan Electric Company (MET) applied to FERC for authorization to recover in electric transmission rates: (1) up to $15 million in costs associated with the construction of new transmission facilities and the deployment of advanced technology to support the development of new electric vehicle (EV) infrastructure in the State of Michigan (EV Infrastructure Pilot Project or Pilot Project); and (2) recovery of 100 percent of abandoned plant costs in the event the EV Infrastructure Pilot Project is abandoned for reasons beyond MET’s control. MET’s EV Infrastructure Pilot Project will facilitate the development and deployment of publicly accessible Direct Current Fast-Charging (DCFC) EV stations to serve long-haul medium- and heavy-duty commercial vehicles, trucks, and buses, and will provide data and information needed to assess how electrification trends and the deployment of EV infrastructure may impact the operation and reliability of the interstate transmission grid regulated by FERC.  METC can already recover the costs of the Pilot Project through its existing formula rate. However, the 2009 Smart Grid Policy Statement allows applicants like METC to submit a section 205 filing to provide “the assurance of cost recovery” and to mitigate against the risk of “future review and challenge.”

Paul Dumais's picture
Thank Paul for the Post!
Energy Central contributors share their experience and insights for the benefit of other Members (like you). Please show them your appreciation by leaving a comment, 'liking' this post, or following this Member.
More posts from this member
Discussions
Spell checking: Press the CTRL or COMMAND key then click on the underlined misspelled word.

No discussions yet. Start a discussion below.

Get Published - Build a Following

The Energy Central Power Industry Network is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.

If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.

                 Learn more about posting on Energy Central »