A Model for Reducing Storm Recovery Time
Dominion shares their “lessons learned” on a very successful strategic undergrounding program. Early-on they ....”found that SAIDI just was not the best measure for big storms. TLR measures the time from last out to last restored.” TLR is “total length(time) of restoration”. See their great customer video at https://lnkd.in/gVHpiVG.
As of September 2020, Dominion Energy has invested US$748 million and moved nearly 4000 separate tap lines, totaling 1502 miles (2417 km), underground. By converting these tap lines to underground, Dominion Energy has, in essence, eliminated 2139 annual events.
Discussions
No discussions yet. Start a discussion below.
Get Published - Build a Following
The Energy Central Power Industry Network is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.
If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.
Sign in to Participate