FERC Staff Report on Barriers to High Voltage Transmission Projects

Paul Dumais's picture
CEO, Dumais Consulting

Owner and CEO of Dumais Consulting (www.DumaisConsulting.com) which provides expert ratemaking services to energy companies. Dr. Dumais is a ratemaking and regulatory expert who specializes on...

  • Member since 2018
  • 158 items added with 121,007 views
  • Aug 20, 2020
  • 733 views

In June 2020, FERC Staff issued a report on barriers and opportunities for high voltage transmission to the Committees on Appropriations of Both Houses of Congress.  Staff concludes that high voltage transmission can improve the reliability and resilience of the transmission system by allowing utilities to share generating resources, enhance the stability of the existing transmission system, aid with restoration and recovery after an event, and improve frequency response and ancillary services throughout the existing system. High voltage transmission also provides greater access to location-constrained resources in support of renewable resource goals. It also offers opportunities to meet federal, state and local policy goals.  Staff found that while transmission development opportunities exist, there are also barriers which make development of high voltage transmission challenging. For instance, siting of high voltage transmission, generally an area of state jurisdiction, requires navigating each state process or multiple state processes for an interstate high voltage transmission facility. Various other authorizations and reviews are also generally required at the federal, state, and local levels. Additionally, the time required to develop a high voltage transmission facility that meets mandatory Reliability Standards, maximizes system benefits, and strikes a balance among interested stakeholders (including states) can be in excess of a decade.  Specific to the nation’s transportation corridors, there are several federal and state actions intended to create opportunities for energy infrastructure development, including high voltage transmission, in these corridors. However, future transmission development in existing transportation corridors may be restricted by routing limitations, including state and local prohibitions and restrictions, and safety and technical considerations. 

Discussions

No discussions yet. Start a discussion below.

Paul Dumais's picture
Thank Paul for the Post!
Energy Central contributors share their experience and insights for the benefit of other Members (like you). Please show them your appreciation by leaving a comment, 'liking' this post, or following this Member.
More posts from this member

Get Published - Build a Following

The Energy Central Power Industry Network is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.

If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.

                 Learn more about posting on Energy Central »