New York State Goes Even Bigger On Offshore Wind

Daniel Spitzer's picture
Partner Hodgson Russ LLP

Dan concentrates his practice on issues involving involving environmental law, renewable energy, sustainable development, land use law, municipal law, and real estate development. His practice...

  • Member since 2020
  • 58 items added with 48,054 views
  • Jan 14, 2021
  • 665 views

On January 13, 2021, Governor Andrew Cuomo of New York State announced by far the largest offshore wind award set by any state in U.S. history, picking two projects that together are expected to provide 2,490 megawatts (“MWs”) of capacity and more than 2,500 good-paying jobs. This announcement, resulting from the New York State Energy Research and Development Authority’s (“NYSERDA”) “Round 2” solicitation, positions New York as the undeniable center of gravity for the burgeoning U.S. offshore wind industry, which is expected to accelerate even faster in 2021 with support from the incoming Biden administration.

The awarded projects – Empire Wind II (1,260 MWs) and Beacon Wind (1,230 MWs) – were both proposed by Equinor, the large Norwegian energy company (formerly Statoil). Equinor’s press release regarding these awards is here, and Equinor’s publicly available proposal document, which outlines the projects, is available here. As part of Equinor’s proposal, it promised to build out the South Brooklyn Marine Terminal facility, creating 1,200 jobs and what could be the largest offshore-wind focused port facility in the United States; and also to base turbine construction operations at the Port of Albany, supporting 500 jobs and injecting significant investment into that upstate region. Equinor’s plan to use the Port of Albany is on top of its commitment to use the Port of Coeymans, just downstream on the Hudson River from Albany, to construct its gravity-based foundations for the Empire I project.

These projects are in addition to New York’s “Round 1” projects that totaled 1,696 MWs: the Empire I Project, in development by Equinor, and Sunrise Wind, in development by Orsted and Eversource, the contracts for which were finalized in October 2019. Together, all four projects will contribute more than 4,000 MWs of capacity to the State’s mix, significant progress after only two solicitations to the State’s 9,000 MW requirement for projects online by 2035 and a major boost to the State’s concerted effort to clean its downstate electricity system, the vast majority of which is currently powered by fossil fuel generation.

Next steps for these projects will be the negotiation of offshore wind renewable energy credit (“OREC”) contracts with NYSERDA, pursuant to the Public Service Commission’s April 23, 2020 Order, and submission of a Construction and Operation Plan (“COP”) for consideration and approval by the Bureau of Ocean Energy Management (“BOEM”) within the U.S. Department of the Interior.

While further details of the awards are still to be rolled out, it is expected that contract negotiations between Equinor and NYSERDA will proceed apace this winter, with finalization of those contracts in the coming months. Equinor will also commence even more extensive efforts to prepare its COP and line up workforce and supply agreements, among the range of other project development tasks. Commercial operation of these projects is expected in the mid-2020s, in plenty of time to contribute to the State’s requirement under the 2019 Climate Leadership and Community Protection Act of 70 percent renewable energy consumption by 2030.

Daniel Spitzer's picture
Thank Daniel for the Post!
Energy Central contributors share their experience and insights for the benefit of other Members (like you). Please show them your appreciation by leaving a comment, 'liking' this post, or following this Member.
More posts from this member
Discussions
Spell checking: Press the CTRL or COMMAND key then click on the underlined misspelled word.

No discussions yet. Start a discussion below.

Get Published - Build a Following

The Energy Central Power Industry Network is based on one core idea - power industry professionals helping each other and advancing the industry by sharing and learning from each other.

If you have an experience or insight to share or have learned something from a conference or seminar, your peers and colleagues on Energy Central want to hear about it. It's also easy to share a link to an article you've liked or an industry resource that you think would be helpful.

                 Learn more about posting on Energy Central »