Celtic Sea | Offshore Wind Leasing Round 5

 

 

Offshore Wind Leasing Round 5: October 2023, Offshore Wind 

 

 Offshore Wind Leasing Round 5:

  • The outer boundary of the area containing the PDAs remains unchanged, as do the key minded-to technical parameters like separation distances between adjacent projects.
  • Round 5 will bring to market three larger PDAs, rather than four PDAs.
  • Up to 1.5GW could be feasible in each new PDA, providing up to 4.5GW in total, instead of the previously expected 4GW.
  • Each PDA will have one winner.
  • Development of each PDA may occur in multiple projects or phases of at least 300MW as previously advised (up to a maximum of three projects or phases).

 

 

The Celtic Sea, Floating Wind and Hydrogen

 

 

 